April 23, 2024

Coring Completion/Plumbing Rough in

Holes are now cored at 1881 Yonge. Plumbing and framing scheduled to be completed on May 6th 2024. We will then have inspections for plumbing and […]
April 19, 2024

Coring Day 2 Update

Coring and underground plumbing are underway! Approximately 50 holes will be drilled through the concrete. Concrete is between 10-15 inches wide. Plumbing piping has been delivered […]
April 15, 2024

Monolithic Floors Armstrong

We were advised for surgical floors it is best to have a monolithic roll up floor choice. Armstrong floors is a very popular choice for health […]
April 15, 2024

April 15th Coring Update

Our coring locations have been approved by building management. Coring to take place Wednesday overnight.   Coring locations diagram  
March 25, 2024

March 25th Goderich Update

We are into the finishing stages of the Goderich Project. Painting is underway. After painting, we will add the ceiling. Then we will add the floors. […]
February 29, 2024

Goderich Update- Feb 29

We are entering into the final 2 stages of the project. Plumbing and electrical rough ins will be complete. In the next couple of weeks we […]
February 29, 2024

Commencement of work

Tomorrow, we will be meeting with the building management to go over the entire scope of the project. We are going to start by getting the […]
February 14, 2024

February 14th Update

Drs. Larsen and Hammad came to site today. Requested that we make the sterilization centre bigger. We will make sterilization centre 11′ wide. Drawings have been […]
February 13, 2024

Feb 13th update

Concrete pour to be completed today. Framing to be completed in next few days. Will enter next phase of construction which is “Final Rough In” All […]