Coring Completion/Plumbing Rough in
Holes are now cored at 1881 Yonge. Plumbing and framing scheduled to be completed on May 6th 2024. We will then have inspections for plumbing and
Approval from management to start coring to floor underneath starting the night of April 17th
Holes are now cored at 1881 Yonge. Plumbing and framing scheduled to be completed on May 6th 2024. We will then have inspections for plumbing and
Coring and underground plumbing are underway! Approximately 50 holes will be drilled through the concrete. Concrete is between 10-15 inches wide. Plumbing piping has been delivered
We were advised for surgical floors it is best to have a monolithic roll up floor choice. Armstrong floors is a very popular choice for health
Our coring locations have been approved by building management. Coring to take place Wednesday overnight. Coring locations diagram
Tomorrow, we will be meeting with the building management to go over the entire scope of the project. We are going to start by getting the
We need to collect information for the ministry of Health application for X-rays and ct scans at 1881 We need to collect this information started this